Data Center Timelines Are at Risk Due to Labor Shortages

Published: Last checked:

Rising construction bids, expected to climb 4.2% in 2027, along with skilled labor shortages and power-readiness gaps, are increasing data center costs and schedule risk, especially in Southern US markets. Facilities may be nearly complete but delayed by unavailable commissioning crews, while adding workers can raise costs unless designs, materials, and sequencing are coordinated.

JLL expects national tender prices, what contractors bid for projects, to rise 4.2% in 2027, up from 3.1% in 2026 and above the 2% to 3% pre-2020 norm. The 2027 environment combines higher construction bids with intensifying competition for specialized workers, especially in Southern US markets where demand for facilities and power infrastructure already strains workforce capacity.

Data Center Timelines Are at Risk Due to Labor Shortages

Factual Summary

ElementSource detailWhy it matters
Tender pricesTender prices, what contractors bid for projects, rise 4.2% in 2027 versus 3.1% in 2026 and 2% to 3% before 2020; applies to broader construction market, not data centers alone.Bidding pressure is not only a data center issue; contractors across construction are repricing risk.
Regional loadThe South is expected to contribute more to nonresidential construction growth than any other US region and carry the heaviest workload per worker by 2028, driven by data centers, power projects, and public civil works.Data center demand overlaps with power and civil work, intensifying competition for scarce crews.
Labor qualityMatthew Giddings, JLL executive director of technical services, told Data Center Knowledge that developers risk underestimating the cost of assembling qualified crews; the issue is qualified workers in the right location at the right time.Budget impact extends beyond wage rates to overtime, travel, lodging, and relocation premiums.
Project scaleEmerging data center markets may lack workforce capacity to support multiple hyperscale developments at once. Campuses increasingly include substations, utility infrastructure, and dedicated generation, requiring thousands of workers over multiyear construction programs.Workforce planning must happen alongside site selection, permitting, and utility strategy.
Power and commissioningUtilities need crews for transmission lines and substations, while developers need electrical trades to build and energize facilities; those labor pools are not interchangeable. Facilities can be substantially complete with power available yet remain months from operation because qualified commissioning personnel are unavailable.Schedule risk can shift from construction to specialized technical readiness.
Cost inputs and accelerationJLL identifies metals, energy-intensive products, and related building packages as cost pressure. Tender prices trail input costs by three to six months, so late 2026 increases affect early 2027 bids. For AI-focused campuses, earlier operation may justify extra spending, but only if it changes the opening date.Adding construction labor does not solve transformer delivery, utility energization, or commissioning constraints.

Labor Capacity Becomes the Core Cost Driver

Giddings warned that adding crews can raise costs without improving productivity when designs, materials, and construction sequencing are not coordinated. Developers are already paying overtime and covering travel, lodging, and relocation premiums to bring specialists into markets without enough local labor. Early relationships with trade schools, community colleges, and apprenticeship programs can build local capacity, but waiting until construction is near means competing for workers already committed elsewhere.

Power Readiness Is Not Construction Readiness

A campus can be substantially complete and still fail to operate if utility work, equipment procurement, construction, and commissioning are not aligned in a single schedule. Giddings described situations where facilities were substantially complete and power was available, yet operation remained months away because qualified commissioning personnel were unavailable. The staffing pools for utility transmission and substation work are separate from the electrical trades that developers need to build and energize facilities.

Uncertainty Is Priced Into Bids

Contractors are not only passing through higher input costs; they are pricing risks they cannot confidently assess. When asked to commit to a guaranteed price or delivery date before design is fully developed or procurement risks are understood, contractors account for that uncertainty. Early contractor involvement, clearer procurement plans, and an experienced owner's team can improve pricing predictability. Established data center contractors with substantial backlogs can be selective, making it harder for owners to pass unresolved project risks downstream at low cost.

Acceleration Only Works If It Targets Bottlenecks

Prefabricated electrical assemblies and standardized cooling infrastructure can reduce on-site labor needs, but manufacturers still face staffing and capacity constraints. Repeatable designs deployed across campuses tend to add more value than isolated prefabrication decisions. For AI-focused campuses, earlier operation can justify substantial additional spending, but developers should weigh acceleration against financing costs, customer commitments, equipment deployment, and revenue lost through delayed occupancy. The calculation depends on whether added spending actually changes the opening date. More construction labor offers little benefit if equipment delivery or commissioning determines when the facility can operate. Overtime and manpower do not help if transformer delivery, utility energization, or commissioning is the true constraint. Successful acceleration targets actual bottlenecks rather than simply increasing construction spend.

Neutral Pros and Cons

Pros:

  • Single-schedule coordination can reduce commissioning delays.
  • Early contractor involvement can improve price predictability.
  • Repeatable campus designs can improve labor efficiency more than isolated prefabrication.
  • Local workforce pipelines can reduce relocation premiums.

Cons:

  • Southern US markets face heavy workload per worker by 2028.
  • Qualified commissioning personnel are not interchangeable with utility or electrical construction crews.
  • Contractor uncertainty can raise bids even when design and procurement risks remain open.
  • Acceleration spending may not shorten timelines if equipment or energization is the bottleneck.

Limitations

JLL's 4.2% 2027 tender-price forecast applies to the broader US construction market rather than data centers alone. The South's projected nonresidential growth and heaviest workload per worker by 2028 reflect expected demand from data centers, power projects, and public civil works, but not every emerging market will face the same constraint. Timing risk depends on project-specific design maturity, procurement readiness, transformer delivery, utility energization, equipment delivery, and commissioning staffing.

FAQ

Why do data center bids rise when labor is the issue?
Because developers may pay overtime, travel, lodging, and relocation premiums to find qualified workers in the right location at the right time, and contractors price uncertainty when design or procurement risks are not settled.

Does prefabrication remove labor risk?
It can reduce on-site labor requirements, but manufacturers still face staffing and capacity constraints. Repeatable designs across campuses are more valuable than isolated prefabrication decisions.

When is extra spending justified?
For AI-focused campuses, earlier operation may justify additional spending only if the spending changes the opening date. More construction labor helps little if transformer delivery, utility energization, or commissioning determines operation.

Sources:

  • JLL, 2027 US Construction Perspective.
  • Data Center Knowledge interview with Matthew Giddings, JLL executive director of technical services.
  • Related headlines referenced in the source: Winning Data Center Bids Starts with the Investment Tax Credit; Data Centers Bring Boom Times, But Will Gains Last?; Data Center Developers Face Tighter Margins as Construction Costs Rise.

Last updated: 2027

Spec tagsData Center ConstructionLabor ShortagesConstruction CostsPower ReadinessProject Timelines